The construction of the network producing hydrogen nitride, methanol and grained carbamide. OJSC “Ammony” is going on: piling has been completed
29 November 2012, Thursday
2658 piles were driven at all the facilities of the network.
General contractor CNCEC (China) is responsible for carrying out work at 59 facilities including 22 facilities being process racks, and in underground pipelines. Most of the work done is concreting and backfilling of foundations of structures and racks. 11.900 m3 of cast-in-situ concrete were placed and more than 145 thousand cubic meters of foundations were backfilled.
8353 long meters of underground pipes of different diameters were installed; more than 90% of hydraulic testing for the sectors was carried out.
More than 1.700 tons of metal structures were transported to the site, of which 1.350 tons were delivered by “Ak Bars Metal” LLC. The erection of the metal structures of two racks began.
Russian contractor “NIIK” OJSC (Dzerzhinsk) is responsible for carrying out work at 25 facilities. Underground pipelines are being installed by Multi-Industry Association “Inshaat” LLC (Naberezhnye Chelny) in the area of the foreign contractor.
“Kamgesenergostroi” OJSC is installing the foundations of facility 92/01 that is a warehouse for carbamide. 1654 cubic meters of concrete were placed.
The work on the perimeter lighting was completed. “PES” LLC provided temporary power supply.
Off-site water supply network B1 and B7 are being installed. Investment Holding Company “Tatgazinvest” welded and laid 9000 long meters of the pipe with the diameter of 630 mm and 8100 long meters of the pipe with the diameter of 160 mm.
Process equipment of the future plant is being delivered.
In the Republic of Tatarstan, work has been completed on the municipal infrastructure modernization program with the participation of funds from the Territorial Development Fund.
In total, 128.3 km of heating, water supply and sanitation networks have been built and upgraded in the region under this program since 2023. Thanks to this, the quality of public services has improved for 1.9 million residents of the region.
In Tatarstan, the minimum contribution for major repairs in apartment buildings in 2025 increased by 10% — from 7.7 to 8.47 rubles per 1 square meter of area. The corresponding resolution of the Cabinet of Ministers of the Republic of Tatarstan was signed by the Prime Minister of the Republic Alexey Pesoshin.
The number of users who have installed the Public Services mobile application on their electronic devices.The number of houses in the Republic of Tatarstan has already exceeded 210 thousand.
The project is being implemented by the Ministry of Construction and the Ministry of Finance of Russia to improve the quality of public utilities provided to citizens.