The construction of the network producing hydrogen nitride, methanol and grained carbamide. OJSC “Ammony” is going on: piling has been completed
29 November 2012, Thursday
2658 piles were driven at all the facilities of the network.
General contractor CNCEC (China) is responsible for carrying out work at 59 facilities including 22 facilities being process racks, and in underground pipelines. Most of the work done is concreting and backfilling of foundations of structures and racks. 11.900 m3 of cast-in-situ concrete were placed and more than 145 thousand cubic meters of foundations were backfilled.
8353 long meters of underground pipes of different diameters were installed; more than 90% of hydraulic testing for the sectors was carried out.
More than 1.700 tons of metal structures were transported to the site, of which 1.350 tons were delivered by “Ak Bars Metal” LLC. The erection of the metal structures of two racks began.
Russian contractor “NIIK” OJSC (Dzerzhinsk) is responsible for carrying out work at 25 facilities. Underground pipelines are being installed by Multi-Industry Association “Inshaat” LLC (Naberezhnye Chelny) in the area of the foreign contractor.
“Kamgesenergostroi” OJSC is installing the foundations of facility 92/01 that is a warehouse for carbamide. 1654 cubic meters of concrete were placed.
The work on the perimeter lighting was completed. “PES” LLC provided temporary power supply.
Off-site water supply network B1 and B7 are being installed. Investment Holding Company “Tatgazinvest” welded and laid 9000 long meters of the pipe with the diameter of 630 mm and 8100 long meters of the pipe with the diameter of 160 mm.
Process equipment of the future plant is being delivered.
The annual All-Russian vote on the selection of facilities for landscaping in the coming year within the framework of the federal project "Creating a comfortable urban environment" is starting in the Republic of Tatarstan.
In August, the Kamashevo Landscape Park will be built on the site of the former Khimik stadium in Mendeleevsk.
The territory is located in the central part of the city and consists of a football field with a running track with an area of over 1 hectare. The site is overgrown with wild shrubs and trees, and they are currently being dismantled and the vegetation layer of the soil is being removed.
From May 30 to May 31, Voronezh will host the largest professional event in the field of architecture and urban development in the regions of Central Russia - the architectural forum "Architecture of the VRN".
Major repairs of the Dubok children's health camp are underway in the Alekseevsky district of Tatarstan. The children's camp is located northwest of the village of Bilyarsk.
According to the project, the builders will renovate two dormitories and a canteen building. Roofing is currently being installed in the dormitories and the floors are being renovated. Roofing works are underway in the canteen building. The total percentage of the facility's readiness is 60%.
SUBSCRIBE FOR NEWS
All content on this site is licensed under
Creative Commons Attribution 4.0 International
If you see a mistake,
please select the word or sentence and press CTRL+ENTER