The head of the Republican Ministry of Construction Marat Aizatullin told about the programs for the construction of socio-cultural facilities, modernization of communal infrastructure and landscaping at a weekly meeting in the Government House of the Republic of Tatarstan.
In the field of education, the construction of 11 schools continues, the work of contractors has been completed by 79%. The construction of two kindergartens continues. The readiness of the "transitioning" preschool institution is estimated at 78%. The work on the second garden was completed by 31%.
In the field of healthcare, according to 2 programs, the construction of 47 paramedic-obstetric stations is provided - 70% of the work volume has been completed here, and 4 polyclinics. The total volume of construction and installation works is 51%. This week, the facility in the Pestrechinsky district was completed.
The branch of culture includes 7 district and rural Houses of culture. To date, 66% of the total amount of work has been completed.
Within the framework of the national project "Ecology", the reconstruction of biological treatment facilities in Kazan continues, 61% completed; recultivation of silt fields in Kazan – by 50%. The performance of work on dismantling pipelines in the Nizhnekamsk reservoir is estimated at 24%. The work on the reclamation of the Samosyrovsky landfill in Kazan was completed by 62%.
Within the framework of 3 improvement programs, work is underway on 68 public spaces. The implementation of them is estimated at 23%.