In the republic, the construction of FAPs under the national project is nearing completion

16 October 2023, Monday

This was reported at a meeting in the Government House of the Republic of Tatarstan by First Deputy Minister of Construction, Architecture and Housing of the Republic of Tatarstan Alexey Frolov. Two federal programs are aimed at supporting housing construction: the federal project "Housing" and the state program "Integrated Development of Rural Areas". The national project "Housing" includes 26 objects, the total implementation is 62%. This week, the construction of two roads in Kazan and in the Laishevsky district was completed.

According to the program "Integrated development of rural areas", 7 sites are being prepared for compact housing development. Of these, one remains in work - in the Sabinsky district with 92% of the work performed.

In the field of healthcare, the volume of work on the construction of 53 paramedic-obstetric stations (FAPs) has been closed by 99%. Of these, 2 remain in operation. Work has been completed in Chistopol, Rybno-Slobodsky, Aznakaevsky and Nizhnekamsk districts. Work on the construction of 4 polyclinics was completed by 89%. The contractors have 2 facilities in Kazan.

Two programs are being implemented in the Culture industry, which include 12 facilities. Their readiness is estimated at 93%. Construction and reconstruction of 7 institutions continues.

The National project "Ecology" includes 4 projects – reconstruction of biological treatment facilities in Kazan – 68% completion, recultivation of silt fields in Kazan – 55% completion, dismantling of pipelines in the Nizhnekamsk reservoir – 96%, recultivation of the Samosyrov landfill in Kazan – 84% completion.

Within the framework of the state program "Reproduction and use of natural resources", the shore protection of the Kuibyshev reservoir near the village continues. The Kama Estuary, the implementation of which is 91%.

Public spaces are being improved within the framework of three programs. Of the 68 objects, 42 are in the work of contractors, the performance is estimated at 91%. Work has been completed in Almetyevsk, Yelabuga, Leninogorsk, Verkhneuslonsky, Alkeevsky and Atninsky municipal districts.