The overhaul of sports facilities has been completed in the republic

18 December 2023, Monday

This, as well as the implementation of republican and federal programs for the overhaul of social facilities in general, was reported by the Minister of Construction, Architecture and Housing of the Republic of Tatarstan Marat Aizatullin at a weekly meeting at the Government House of the Republic of Tatarstan.

In the field of "Healthcare", out of 149 facilities included in three republican and federal programs, it remains to complete repairs in 6 inpatient facilities. The readiness of the facilities is estimated at 90% or higher.

Out of 44 facilities in the Kultura line, 5 contractors remain in operation. Their performance exceeds 90%. The renovation of two rural houses of culture has been completed – in Laishevsky and Kukmor districts. There are also 2 branch educational institutions in operation: the Rodigins Felting Factory cultural heritage site in Kukmor and the museum in Zelenodolsk.

In terms of youth policy, out of 27 facilities, it remains to complete work on the republican program for the repair of psychological and pedagogical Assistance Centers. These are five facilities in Kazan and one in Zelenodolsk. Their performance ranges from 85 to 99%. Work has been completed at the facility in Kazan.

Of the 13 buildings of the military commissariats, work is being completed on 2 sites – in Kazan and Bazarnye Mataki village. The volume of work on them exceeds 90%. Over the past two weeks, 3 facilities have been commissioned in the cities of Nurlat and Naberezhnye Chelny, as well as in the Mendeleevsky district.

Of the 5 buildings subordinated to Rosgvardiya, one remains in operation in Nizhnekamsk. Its readiness is estimated at 96%.

This week, the program for the overhaul of sports facilities was completed with the commissioning of the last one in Kazan.

 

 