Large-scale works on the construction of social and cultural facilities are continuing in the republic

27 May 2024, Monday

Marat Aizatullin, Minister of Construction, Architecture and Housing of the Republic of Tatarstan, reported on how programs in the construction industry are being implemented in Tatarstan at a meeting in the Government House of the Republic of Tatarstan.

In the field of "Education", work continues on the construction of 11 schools and outbuildings, for which the total completion is 39%. The volume of construction and installation work in 10 kindergartens has been closed by 30%.

In healthcare, 46% of the planned volume was completed during the construction of FAPs, and 44% for other medical institutions.

Work continues on the construction of 4 football arenas for sports facilities. The completion rate is 9%. Work is also underway on 7 universal sites. The total completion of the program is 6%.

The construction of a ski and roller track in Kukmor and the administrative building of the existing football field in the village has been completed by 7%. Apastovo, which is conducted within the framework of the state program "Integrated rural development".

In the field of Youth Policy, construction and installation work on 6 children's camps included in the republican program has been completed by 22%. The construction of a youth center included in the federal program in the village is estimated at 15%. Rybnaya Sloboda.

In the "Culture" industry, the fulfillment of 3 objects is 22%.

According to the objects of the Ecology industry, work is underway on the reconstruction of Biological treatment facilities - 81%, on the reclamation of silt fields – 67%, on the reclamation of lands disturbed by oil-containing pollution in the village of Shemordan of Sabinsky district - 80%.

Within the framework of sectoral republican programs, the construction of executive committee buildings (readiness in 37%) and comprehensive public service points (53%) is underway.

Work is underway to improve public spaces. Of the 64 facilities, work is underway on 45. The total completion of the program is 9%. Work on the remaining 19 sites will begin in the next 2 weeks.