In Tatarstan, 5 kindergartens are being built in 2025 with a total financing of 738 million 144 thousand rubles. This was reported last Saturday at a meeting in the Government House of the Republic of Tatarstan by the Minister of Construction, Architecture and Housing and Communal Services of the Republic of Tatarstan Marat Aizatullin.
Rustam Minnikhanov held a videoconference meeting with all municipal districts of the Tatarstan.
Construction and installation work was completed by 42%, the dynamics exceeded 4.7%.
"The construction of a preschool for 80 children in the village of Apastovo has been completed – it was carried out under the state program "Integrated Rural Development," said the head of the Ministry of Construction of the Republic of Tatarstan. - Two extra-programmatic facilities are also being built: in the Vysokogorsky district for 120 places and the housing complex "33 military town" of Kazan for 220 places.
In addition, according to Marat Aizatullin, the construction of two kindergartens is included in the federal Family Support program, which this year was included in the new national Family project: 340 places in the village of Kuyuki in the Pestrechinsky municipal district and 260 places in the village of Oktyabrsky in the Zelenodolsk municipal district. These two objects are transients. The total amount of financing for the current year is more than 104 million rubles.
It should be recalled that among the main goals of the national Family project is to combine measures to support young, large families so that they can combine education and child rearing.
In the photo: the construction of a kindergarten in the village of Oktyabrsky