The second stage of the large-scale reconstruction of the water pipeline, which began in 2025 under the national project "Infrastructure for Life", continues in Leninogorsk.
The pumping station with a total length of 30.5 km was built in the 1990s. During operation, its wear reached 85%.
7.5 km of networks will be updated in 2025.
8.2 km will be replaced this year, with over 333 million rubles allocated for this purpose. The remaining section is planned to be included in the 2027 program.
As a result, 68,000 residents of Leninogorsk and 8 rural settlements of the district will be provided with household drinking water and fire-fighting water supply.
Construction and installation works are performed by the general contractor "Energy Service Company". Among the major projects implemented by the company is the reconstruction of gas consumption networks with the installation of a block-modular boiler house in Leninogorsk and a central boiler house in Aznakayev.
Excavator operator Ara Yelchyan is actively involved in the modernization of the Leninogorsk water pipeline. Ara Zhoraevich has been working in the housing and communal services sector for more than 9 years, and in Energy Service Company LLC for 3 years. Thanks to his experience, good coordination and eyesight, the pipeline is laid efficiently and on time. Two methods are used: horizontal inclined drilling – 2.4 km and open–cut drilling - 5.8 km.
It is planned to complete the current year's plan in August, now the facility is 85% ready.
Recall that in 2026, according to the national project "Infrastructure for Life" in Tatarstan, 17 municipal facilities will be modernized for a total amount of 2.5 billion rubles.