Construction of the infrastructure facilities of the special economic zone discussed at the meeting in “Alabuga”
7 December 2012, Friday
The issues of the infrastructure facilities construction of special economic zone “Alabuga” were discussed at the meeting with contractors. The meeting was held by Deputy Minister of Construction, Architecture and Housing of the Republic of Tatarstan Yu.L.Alyashev in IP SEZ “Alabuga”.
General contractors of “Kamgesenergostroi” OJSC and “Trest Kamdorstroi” CJSC are completing the work according to the contracts signed in 2012 and preparing the facilities for the commissioning to the customer. As of today, from the beginning of the year, 336.288 mln.rubles have been disbursed, including 256.464 mln. rubles by “Kamgesenergostroi” OJSC and 79.824 mln. rubles by “Trest Kamdorstroi” CJSC. The plan for construction and installation work in November was exceeded by 30%. “Kamgesenergostroi” OJSC completed the installation of equipment РП-13, and is preparing for the final inspection carried out by the State Construction Supervision Inspectorate of the Republic of Tatarstan, and voltage supply. “Trest Kamdorstroi” CJSC is reconstructing the overhead transmission line through the motorway M-7. The completion date is December 20th, 2012.
Currently, in order to ensure the implementation of the program on the construction and installation work for the next year, the contractors are preparing for the participation in public tenders for the construction of the infrastructure facilities of the special economic zone.
The residents of SEZ “Alabuga” are keeping the pace of the plants construction.
As a part of the construction of the plant for processing carbon fiber “Alabuga-Volokno” LLC contractor “Multifunctional Association Inshaat” CJSC is installing sandwich panels of the production building. Simultaneously with the construction and installation work the technological equipment to be installed in March 2013, is being delivered. The production is to be started up in the 4th quarter of 2013.
Resident “Sariya Bio Industris Volga” (“Stroimontazh-Engineering” LLC being a contractor) almost completed the construction and installation work. The resident is implementing the project for the production of technical oil and feed meal. The production is to be started up in the 1st quarter of 2013.
Resident “Automativ Glass Alyans Rus”CJSC building a plant for the production of automotive glass completed the installation of the foundations and cast-concrete work; 75% of wall sandwich panels and 55% of the roof steel structures have been installed. The production is to be started up in the second half of 2013.
“Trakya Glass Rus”CJSC is implementing the project for the production of building (flat) glass, mirrors and coated glass. Currently, contractor “TEPE Insaat” completed the installation of the foundations of the production building, concrete work is being carried out and steel structures are being installed. The production is to be started up in the 1st quarter of 2013.
As of today, “Kastamonu Integreyted Vud Indastri” LLCbuilding the plant for the production of MDF boards (“Kompas Engineering” LLC being a contractor) completed the installation of the columns and steel structures of the production building, is constructing the intrasite the runoff water system, and installing concrete floors and sandwich panels. The construction of the administrative building with a dining room is 20% complete.
Today, a briefing was held at the Government House of the Republic of Tatarstan on ensuring the smooth operation of road services and housing and communal services in Tatarstan during the New Year holidays. Damir Shaidullin, First Deputy Minister of Construction, Architecture and Housing of the Republic of Tatarstan, spoke at the event.
The Head of the Ministry of Construction of the Republic of Tatarstan, Marat Aizatullin, reported on housing construction in Tatarstan today at a meeting in the Government House of the Republic of Tatarstan. Rustam Minnikhanov held a videoconference meeting with all municipal districts of the Tatarstan.
All 14 programs for the construction of social and cultural facilities have been completed in full within the limits of the current year. This was announced today at a meeting in the Government House of the Republic of Tatarstan by the Minister of Construction, Architecture and Housing and Communal Services of the Republic of Tatarstan Marat Aizatullin.
A complex of works has been carried out in the three-storey school building with a total area of 4,941 square meters: the roof has been updated, the premises have been decorated, internal and external engineering networks have been installed, elevator equipment has been installed.