Mazit Salikhov held a republican headquarters to prepare for the heating period

10 August 2023, Thursday

The readiness of the housing stock, social facilities and heat supply for the upcoming heating period was discussed today at a working meeting in the Ministry of Construction of the Republic of Tatarstan. Deputy Minister of Construction, Architecture and Housing of the Republic of Tatarstan Mazit Salikhov held a regular meeting of the headquarters.

 

According to the operational information entered by the municipal districts into the "Monitoring of Housing stock" system, a total of 2,747 boiler houses have been prepared, which is 88%.

 

2,891 educational facilities are ready to start heating, or 88.8%. More than 90% of the readiness of healthcare facilities. Also, more than 90% of social facilities are prepared for the future heating period along the lines of culture, sports and youth.

 

Flushing and crimping of intra-house central heating systems was performed in 9,891 houses, ventilation ducts of intra-house systems were checked in 15,722 houses. As a percentage, the data is more than 80%.

 

Currently, readiness passports are issued for 13 thousand 161 MCD, which is 73.9%.

 

At the conclusion of the speech, Mazit Salikhov drew the attention of the heads of municipalities to the need to strengthen the work in which the preparation of facilities for the launch of heat has not been completed. He also recalled the timely introduction of information on the implementation of measures to prepare for the heating period in the information and analytical system "Monitoring of housing.

 

SUBSCRIBE FOR NEWS
All content on this site is licensed under
Creative Commons Attribution 4.0 International