Minister of Construction, Architecture and Housing and Communal Services of the Republic of Tatarstan Marat Aizatullin reported on the implementation of the programs for the overhaul of socio-cultural facilities and apartment buildings today at the republican meeting in the Government House of the Republic of Tatarstan.
Rustam Minnikhanov held a meeting of the Rais of Tatarstan. The meeting was attended by the Prime Minister of Tatarstan Alexey Pesoshin.
In terms of the overhaul of educational facilities, 7 republican and federal programs are being implemented. The performance of work in 43 general education institutions is 99%. Contractors still have 14 facilities in 5 municipalities, 3 of them in Kazan, 6 in Naberezhnye Chelny, 3 in Nizhnekamsk, one each in Vysokogorsky and Pestrechinsky districts.
In 7 kindergartens, the work was completed by 94%.
The program for 143 school catering units is 99% completed. Contractors still have 8 facilities in 5 municipalities, 3 of them in Kazan, 2 in Naberezhnye Chelny and one facility each in Pestrechinsky, Chistopolsky, Mendeleevsky districts.
92% of the work on the overhaul of 9 resource centers has been completed. This week, 2 facilities have been completed in the Kukmorsky and Buinsky districts.
Of the 4 dormitories of secondary vocational education being repaired this year, work is being carried out on 2 - in Bugulma and Kazan. The overall performance on them is 96%.
In the healthcare industry, three federal and republican overhaul programs are being implemented, which include 118 primary care institutions. The work as a whole is 98% completed. This week, contractors reported on the delivery of three facilities in Yelabuga, Nurlat and Aktanysh districts. The overhaul of 31 hospitals was completed by 77%.
Four federal and republican programs are being implemented in the culture industry. 34 rural Houses of culture have been repaired by 73%. This week, the repair of facilities in the Kaibitsky, Spassky, Cheremshansky and Baltasinsky districts has been completed. Construction and installation works at 10 branch educational institutions were completed by 67% of the planned volume.
According to the program of capital repairs of apartment buildings, the total performance of construction and installation works is 95%. Including the performance of seasonal types - 97%. Work on 373 objects has been fully completed.