98 percent of boiler houses in the republic are ready to start heating

31 August 2023, Thursday

Tatarstan Mazit Salikhov held a regular meeting of the Republican Headquarters on preparation for the heating period of 2023/2024.

According to operational information, a total of 3,169 boiler houses have been prepared in the Republic of Tatarstan, which is 98%. In 37 districts, the work on the preparation of boiler houses has been completed.

For educational facilities, 3,224 objects out of 3,257 objects are ready, which is 99%, 35 municipal districts have completed the preparation.

In healthcare, 1,974 objects out of 1,980 objects have been prepared, which is also 99%. The work has been completed in 40 districts.

1,895 cultural objects out of 1,915 are ready for the heating period, in 38 districts of the republic the work on preparing for winter has been completed.

Sports and youth facilities in Tatarstan are 98% and 99% ready, social protection facilities are 100% ready.

Upon presentation of passports of readiness of apartment buildings for the heating period, according to the operational data of the State Housing Inspectorate, readiness passports were issued for 16 thousand 508 MCD. Which is 93%.

Representatives of the Alekseevsky, Vysokogorsky and Laishevsky municipal districts reported on the results of preparations for the upcoming launch of heat during the meeting.

 