The implementation of construction programs in the republic is in full swing, ready-made facilities are handed over by contractors every week, Minister of Construction, Architecture and Housing of the Republic of Tatarstan Marat Aizatullin said at a republican meeting in the Government House of the Republic of Tatarstan.
Rustam Minnikhanov held a meeting. The meeting was attended by the Prime Minister of Tatarstan Alexey Pesoshin.
According to the Minister, in the field of education, within the framework of the national project "Demography", the construction of a kindergarten in the 59th quarter of Kazan continues. Its implementation is 68%.
Two programs are being implemented in healthcare. The volume of work on the construction of 53 paramedic and obstetric stations has been closed by 97%. Of these, 7 remain in operation. 84% of the work on the construction of 4 polyclinics has been completed. Contractors are currently working on 2 facilities in Kazan.
Two programs are also being implemented in the "Culture" industry. They include 12 facilities, the readiness of which is estimated at 88%. The construction and reconstruction of 8 institutions continues.
Two federal programs are aimed at environmental protection. According to the national project "Ecology", biological treatment facilities in Kazan are being reconstructed (66% of implementation), the reclamation of silt fields in Kazan (54%), the dismantling of pipelines in the Nizhnekamsk reservoir (70%) and the reclamation of the Samosyrov landfill in Kazan (77%).
Within the framework of the state program "Reproduction and use of natural resources", the shore protection of the Kuibyshev reservoir at the village of Kamskoye Estuary continues. By the current date, the completion is 90%.
Under the republican programs, the construction of 8 buildings of the executive committees of settlements and 10 points of comprehensive public services has been completed. The overall readiness for the construction of 3 indoor football arenas is 91%. This week, the construction of the facility in the village of Pestretsy was completed. Readiness for 6 children's health camps – 74%.
According to the drinking water supply program, the volume of work is 97%. Of the 115 objects, 20 remain in operation. For the reconstruction and construction of gas distribution networks, intra-house gas consumption networks with the installation of boiler houses, one of the 33 objects remains in operation - in the Spassky district, the implementation of it is 31%.
95% of the work has been carried out on the modernization of sewage treatment plants and major repairs of sewerage networks. 3 out of 11 objects remain in operation. This week, work has been completed on 5 objects in the Apastovsky, Mamadyshsky and Zelenodolsk districts. Also this week, the program for the restoration of street lighting has been fully completed.
According to the federal project "Clean Water", work is underway on the construction of a water treatment plant in the village.Alekseevskoye (the volume of work is 87%), water supply networks in the village ofSurovka and Novotroitskoye village of Tukayevsky district (90%) and the two-year object of the program is the water supply system in Nurlat (98%).
According to the new federal program for the modernization of municipal infrastructure, to date, the performance of work on 30 objects is 71%. The facility in Naberezhnye Chelny has been completed this week.