Marat Aizatullin reported on the implementation of republican and federal programs in Tatarstan

27 November 2023, Monday

Minister of Construction, Architecture and Housing of the Republic of Tatarstan Marat Aizatullin spoke about the implementation of program measures for construction in key industries and modernization of engineering infrastructure at a meeting in the Government House of the Republic of Tatarstan.

 

In his report, he noted that for two federal programs aimed at supporting housing construction in part of the federal Housing project, the total implementation is 70%. Over the past 2 weeks, work has been completed at 2 facilities - in Zelenodolsk and Muslyumovsky districts. The state program «Integrated development of rural areas» has been completed this week. Contractors handed over the last object in the Sabinsky district.

 

Within the framework of the national project «Demography» in the field of education, the construction of a kindergarten in the 59th quarter of Kazan continues. Construction and installation work on it was completed by 93%.

 

According to 2 programs in the field of healthcare, one facility remains in operation – a branch of the polyclinic «Salavat Kupere». Its implementation is 92%.

 

Within the framework of two programs implemented in the «Culture» industry, 4 out of 12 institutions remain in operation. In general, the readiness for all facilities is 96%. This week, the construction of a village club in the Kukmor district has been completed.

 

In terms of the implementation of the national project «Ecology», 72% of the work on the reconstruction of biological treatment facilities in Kazan, 61% - recultivation of silt fields in Kazan, 95% - recultivation of the Samosyrov landfill in Kazan. Work has also begun on the reclamation of lands with oil-containing pollution in the village of Shemordan, Sabinsky district, the facility is transitioning to next year.

 

Shore protection of the Kuibyshev reservoir near the village. The Kama Estuary is part of the state program «Reproduction and use of natural resources». By the current date, the implementation is estimated at 93%.

 

22 out of 68 objects are in the work of contractors for the improvement of public spaces. The overall performance for all objects is estimated at 97%. Over the past two weeks, work has been completed in 6 parks: two each in the Nurlat and Almetyevsk districts and one each in the Pestrechinsky and Zelenodolsk districts.

 