Implementation of republican and federal programs continues in the Republic of Tatarstan

13 May 2024, Monday

Minister of Construction, Architecture and Housing and Communal Services of the Republic of Tatarstan Marat Aizatullin reported on the implementation of republican and federal programs for the construction of social facilities and engineering infrastructure at a meeting in the Government House of the Republic of Tatarstan.

Thus, 11 schools and outbuildings are under construction in the education sector (31% completion). Construction and installation work on 10 kindergartens has been completed by 23%.

The completion of work on the construction of paramedic and obstetric stations is 39%. For other medical institutions, construction and installation work reached 42%.

The construction of 4 football arenas continues in the sports industry, the work is 6% completed. The construction of 4 universal sites out of 15 has begun.

Within the framework of the state program "Integrated rural development", the construction of a ski and roller track in Kukmor and the administrative building of the existing football field in the village has begun. Apastovo. The completion rate was 5%.

In the field of youth policy, work is underway on all 7 sites. Thus, the completion of work on the construction of 6 children's camps is 17% (included in the republican program). The volume of construction of a youth center in the village has been closed by 12%. Rybnaya Sloboda (included in the federal program).

In the cultural sector, work is underway on all three objects (17% completion).

In the field of ecology, work continues on the reconstruction of biological treatment facilities (80% completed), on the reclamation of silt fields (67% completed); on the reclamation of lands disturbed by oil-containing pollution in the village of Shemordan, Sabinsky district (79% completed).

Within the framework of two republican programs, the construction of executive committees and points of comprehensive public services is underway. The readiness of the buildings of 7 executive committees is 33%. The work on the integrated service points was completed by 40%.

According to the program for providing the population with drinking water, work is underway at 30 facilities in 20 districts.