Minister of Construction, Architecture and Housing and Communal Services of the Republic of Tatarstan Marat Aizatullin reported on the implementation of capital repair programs for socio-cultural facilities, hydraulic structures and apartment buildings at a meeting in the Government House of the Republic of Tatarstan.
Rustam Minnikhanov held a videoconference meeting with all municipal districts of the Rais of Tatarstan. The meeting was also attended by Prime Minister of the Republic of Tatarstan Alexey Pesoshin, Chairman of the State Council of the Republic of Tatarstan Farid Mukhametshin.
Thus, the overhaul of educational facilities is carried out within the framework of 7 federal and republican programs, which include 185 facilities. The situation is as follows: the completion of work on the overhaul of kindergartens is 53%, the overhaul of schools and educational centers is completed by 29%. Over the past 2 weeks, contractors have commissioned 5 facilities, 3 of them in Naberezhnye Chelny and one each in Kazan and the Yutazinsky district.
Work continues on the repair of food halls in schools - today contractors work in 26 schools out of 94. The total implementation of the program is 4%.
For the facilities of the middle professional level, the situation is as follows: construction and installation works of 4 resource centers have been completed by 37%, work on the repair of dormitories has been completed by 40%.
There are 137 facilities in the Healthcare industry in the program. Of these, work on 82 paramedic and obstetric stations was completed by 72%. Over the past 2 weeks, contractors have commissioned 12 facilities: 4 in the Aktanyshsky district, two each in Vysokogorsky and Aznakaevsky, one each in Cheremshansky, Leninogorsk, Novosheshminsky and Chistopolsky districts. A total of 31 objects have been completed.
The repair work of 25 polyclinics has been completed by 50%. This week, the facility in the Almetyevsk district was completed. Construction and installation work on the repair of 30 hospitals has been completed by 41%.
In the Culture industry, all 5 children's art schools included in the programs are currently being repaired (58% completion), 11 cultural institutions are also being repaired (41% completion).
According to the youth policy, major repairs are being carried out in 4 youth centers (implementation - 20%), in 8 children's health camps (implementation - 17%), the repair of teenage clubs amounted to 30%.
Work is also underway in two centers of psychological and pedagogical assistance. The fulfillment of them is 14%.
The sphere of "Ecology" includes 21 water bodies, of which 17 are already in operation (47% completed). Such types of work as clearing riverbeds and cleaning lakes, repair of hydraulic structures are planned.