Minister of Construction, Architecture and Housing and Communal Services of the Republic of Tatarstan Marat Aizatullin reported on the implementation of capital repair programs for socio-cultural facilities at a meeting at the Government House of the Republic of Tatarstan.
Rustam Minnikhanov held a videoconference meeting with all municipalities of the Rais region of Tatarstan. The meeting was attended by Prime Minister of the Republic of Tatarstan Alexey Pesoshin.
185 facilities are currently being repaired in the field of education. The overhaul of preschool educational institutions has been completed by 96%. This week, work has been completed at 8 sites: one each in Tyulyachinsky, Chistopolsky, Sabinsky, Vysokogorsky, Agryzsky, Kukmor, Atninsky and Drozhzhanovsky districts.
94% of the planned amount of work has been closed to repair schools and educational centers. This week, 9 facilities have been completed: 3 in Kazan, 2 in Zainsk, and one each in the cities of Arsk, Chistopol, Naberezhnye Chelny, as well as in the Almetyevsk district.
97% is the repair of 94 food units. Over the past half month, 34 facilities in 17 municipalities have been completed.
In the healthcare sector, 138 medical facilities are included in the current year's overhaul programs. The repair of 82 paramedic and obstetric stations has reached the finish line - construction and installation work has reached 98% here. 78 facilities have been commissioned, including 10 FAPs completed in the last two weeks in Zainsky, Atninsky, Aksubayevsky, Tyulyachinsky and Mamadyshsky districts.
As for the repair of polyclinics, the total performance of work on 25 facilities amounted to 94%. Two facilities in Kazan were commissioned within a week.
The implementation of program measures for the overhaul of 31 medical hospitals is estimated at 77%. This week, one facility was commissioned in Kazan.
92% of the repairs of 24 objects in the Culture industry are carried out at 5 children's art schools. Construction and installation works have reached 80% for 19 cultural facilities. Over the past two weeks, work has been completed on 3 sites in Vysokogorsky, Rybno-Slobodsky and Agryzsky districts.
The sphere of youth policy includes 28 facilities. Repairs were carried out by 38% for 7 youth centers, 48% for 9 children's health camps, and 70% for 6 youth clubs. 35% of the total volume has been closed for the repair of psychological and pedagogical assistance centers.
21 objects are being implemented in the field of Ecology. The total completion of work on them has reached 85%. Of the 13 completed facilities, 4 contractors have commissioned over the past 2 weeks in Mamadyshsky, Agryzsky, Spassky and Vysokogorsky districts.
Contractors have closed 70% of the planned volume at the facilities of the Ministry of Sports. In two weeks, one facility was commissioned in the Vysokogorsky and Yelabuga districts.