Today, the Ministry of Construction of Tatarstan held an in-person meeting of the Republican Headquarters on preparation for the heating period. It was conducted by Deputy Minister of Construction, Architecture and Housing of the Republic of Tatarstan Mazit Salikhov.
According to the operational information of data monitoring, 3,098 boiler houses have been prepared in the Republic of Tatarstan, which is 96%.
3,261 facilities are ready for education, or 98%; in healthcare, the readiness of facilities is 98% – this is 1961 facilities.
For cultural facilities, 1,896 facilities are 99% ready, social protection facilities are 99% ready, 95% of sports facilities and 93% of youth facilities are also ready for launch.
Sergey Berezhnev, Head of the Contract Execution Control Department of Gazprom Mezhregiongaz Kazan JSC, informed the participants of the meeting about overdue debts of the organizations of the communal complex for consumed natural gas. Enterprises will have to close all debt obligations for consumed gas by next year.
Representatives of the Laishevsky, Bavlinsky, Kukmorsky municipal districts, as well as the city of Kazan, came to the attention of the media with the results of preparations for the upcoming launch of the ship.