The reconstruction of biological treatment facilities in Kazan under the national Ecology project was completed by 96%, construction and installation work on the reclamation of silt fields - by 73%. This was announced by the Minister of Construction, Architecture and Housing of the Republic of Tatarstan Marat Aizatullin at a republican meeting in the Cabinet of Ministers of the Republic of Tatarstan.
Rustam Minnikhanov held a meeting of the Rais of Tatarstan.
In addition, the total completion of construction and installation works on the improvement of 64 public spaces within the framework of the federal program "Formation of a comfortable urban environment" of the national project "Housing and urban Environment" is 95%. Over the past 2 weeks, the improvement of 7 facilities in 7 municipalities has been completed.
According to measures aimed at supporting housing construction, 4 facilities under the federal Housing program remain in operation - 75% of them are fulfilled.
In terms of educational institutions, construction and installation work on the building for primary schools in the Kukmor district is currently continuing, where the completion rate is 72%. The construction of 5 pre-school educational institutions has closed 88% of the total. Over the past two weeks, the construction of a kindergarten for 260 places in the village of Kuyuki in the Pestrechinsky municipal district has been completed.
In the Healthcare sector, out of 53 facilities under construction within the framework of a national project, a state program and two republican programs, work continues on 5 medical institutions, where 63% of the implementation is available.
In the field of sports facilities, 3 football arenas remain in operation - 82% of the completion. This week, the program for the construction of universal sports grounds was completed with the commissioning of an object in Yelabuga.
83% is the completion of work on the construction of a ski and roller track in Kukmor and the administrative building of the existing football field in the village. Apastovo.
According to the youth policy, four out of 6 children's health camps remain in operation. The total implementation of the program is 63%. 65% of the work on the youth center in the village has been completed. Rybnaya Sloboda, which is under construction under the federal program "Modern appearance of rural areas".
For three objects of the Culture industry, the performance was 87%.
According to the two remaining republican programs for the construction of social institutions, one facility remains in operation. This is the building of the executive committee in Cheremshansky district (95% completion) and a comprehensive service point in Nurlatsky district with 97% completion.