According to the national project, sewage networks with a length of 3 km will be replaced in two Naberezhnye Chelny complexes

16 April 2026, Thursday

As part of the modernization of engineering networks of Naberezhnye Chelny, in March, the replacement of the pressure sewer network 17a of the complex and 19 of the complex began. The overhaul is carried out under the national project "Infrastructure for Life" with financing of more than 205.8 million rubles.

According to the State Institution "Main Directorate of Engineering Networks of the Republic of Tatarstan", the steel pipeline, built in 1972, has a wear rate of more than 85%. During operation, the inner surface of the pipes has become overgrown with corrosion products, and waterproofing has been disrupted. As a result, numerous emergency situations were recorded here.

2.9 km of polyethylene pipe will be laid at the facility and 4 pumps will be replaced. Construction and installation work has now been completed by 25%, and completion is scheduled for August.

The modernization of networks in this area will improve the quality of services for 38 123 residents of 17a and 19 complexes of Naberezhnye Chelny.

As previously reported by the head of the Ministry of Construction of the Republic of Tatarstan Marat Aizatullin, this year 15 municipal infrastructure facilities will be repaired in Naberezhnye Chelny under the national project "Infrastructure for Life".