In the village of Lyuga, Kukmor district, builders are overhauling a local club. The facility is included in the federal program "Family values and cultural infrastructure" of the national project "Family" with financing of 30 million rubles.
According to the GISU of the Republic of Tatarstan, dismantling works, installation of roofs and radiators, wiring of heating and water networks have been completed. A floor screed is also made. The insulation of the attic floor, the finishing of the heating station, electrical installation, dismantling and installation of a blind area are currently underway.
After that, the workers will start replacing the windows.
The facility is 64% ready.
As previously reported by the head of the Ministry of Construction of the Republic of Tatarstan, Marat Aizatullin, 6 rural clubs in Mamadyshsky, Kukmorsky (3), Baltasinsky and Arsky districts with total funding of over 195 million rubles will be overhauled in Tatarstan under the national project "Family".