At the construction of the network producing hydrogen nitride, methanol and grained carbamide “Ammony” JSC, in Mendeleyevsk city, they started installing the equipment supplied by foreign contractor MHI (Japan). Also, the contractors are continuing construction and installation work on laying underground pipelines and installation of foundations, the steel structures are being erected; currently there are 750 tons of installed steel structures, and the construction industries delivered 6400 tons. In the area of responsibility of Russian contractor “NIIK” JSC the subcontractors of “Kamgesenergostroi” JSC, “IKhK Tatgazinvest” CJSC, “Alteks-Stroi” LLC and STPK “Povolzhye” LLC are performing the work on trenching, laying of pipelines, installation of reinforced concrete structures, reinforcement, walls concreting, slab lifting in buildings, structures, and off-site facilities, they are finishing the work performed on the administrative and laboratory buildings, residential buildings and on the main office of the plant. As of May 15, 2013, 16 500 m3 of concrete have been accepted and 38 600 linear meters of pipelines have been laid. 1220 workers and 127 units of construction equipment are involved at the construction site. In the near future it is expected to increase the number of workers.