The kindergarten overhaul program has been completed by 61%

14 June 2024, Friday

Minister of Construction, Architecture and Housing and Communal Services of the Republic of Tatarstan Marat Aizatullin reported on the state of work on major repairs of socio-cultural facilities, hydraulic structures within the framework of republican and federal programs at a meeting in the Government House of the Republic of Tatarstan today.

 Rais of the Republic of Tatarstan Rustam Minnikhanov held a meeting.

In the field of Education, major repairs are being carried out within the framework of 7 federal and republican programs, which include 185 facilities. Thus, 61% of the work on kindergartens has been completed, 37% of the work on schools and educational centers has been closed. Over the past 2 weeks, contractors have completed work at the facility in the Rybno-Slobodsky district. For the repair of food units – to date, work is underway in 82 schools. The total completion of the program is 9%.

And construction and installation works on 4 resource centers were completed by 43% for medium-professional level facilities and 60% for the repair of dormitories. This week, contractors completed work at the facility in the city of Zainsk.

137 facilities are included in the Healthcare industry. The completion of construction and installation work at 82 paramedic and obstetric stations reached 80%. Over the past 2 weeks, contractors have commissioned 9 facilities in Aksubaevsky and Muslyumovsky, Nurlatsky, Sarmanovsky, Almetyevsky, Agryzsky and Tetyushsky districts. A total of 40 objects have been completed. 58% of the planned amount of work has been closed for the repair of 25 polyclinics. Construction and installation work on the repair of 30 hospitals has been completed by 47%. This week, contractors completed work at the facility in the Baltasinsky district.

In the field of Culture, all 5 children's art schools included in the programs are currently being repaired, where 63% of the completion is available.

As part of the youth policy, repairs are being carried out in 6 youth centers. The scope of work under the program is closed by 24%. The completion of work in 8 children's camps amounted to 20%. 36% of the construction and installation work was carried out to repair teenage clubs.

Work is also underway in two centers of psychological and pedagogical assistance. The fulfillment of them is 17%.

The sphere of "Ecology" includes 21 water bodies, which will be used for such types of work as clearing riverbeds and cleaning lakes, as well as repairing hydraulic structures. 16 of them are currently in the contractors' work. The overall performance is 56%. This week, work was completed

at two sites in the Vysokogorsky and Cheremshansky districts.

SUBSCRIBE FOR NEWS
All content on this site is licensed under
Creative Commons Attribution 4.0 International