Minister of Construction, Architecture and Housing and Communal Services of the Republic of Tatarstan Marat Aizatullin reported on the implementation of capital repair programs for social and cultural facilities at a meeting at the Government House of the Republic of Tatarstan.
Rustam Minnikhanov held a videoconference meeting with all municipal districts of the Rais of Tatarstan.
Thus, the repair of educational facilities is carried out within the framework of 7 federal and republican programs, which include 185 facilities. There are 21 kindergartens among them - the performance of work on them today is 66%. For 51 schools and educational centers, program activities were completed by 46%. Construction and installation works account for 19% at 94 food units. The work on 4 resource centers has been completed by 50%. For 15 dormitories, contractors have closed 65% of the total amount of work.
In the field of healthcare, major repairs are being carried out at 137 facilities. The implementation of 82 paramedic-obstetric stations reached 87%. The list of ready-made objects has been replenished with 6 objects over the past half a month. Thus, the repair of 46 FAPs has been completed. 65% of the planned volume of work is available for the repair of 25 polyclinics. Work on 31 hospitals accounted for 53% of the total volume.
24 facilities under 3 programs are being repaired in the Culture industry. Currently, all 5 children's art schools provided for in the programs are being repaired, where the implementation is 69%. For 15 cultural institutions, the fulfillment reaches 55%.
In the field of youth policy, repairs were carried out by 26% in 7 youth centers. The readiness of 9 children's camps is 24%. 42% is the completion of construction and installation work on the repair of 6 teenage clubs. The same number of facilities is included in the program of repair of psychological and pedagogical assistance centers - 21% of the total volume is closed here.
In the field of Ecology, according to republican and federal programs, the improvement of water bodies, the clearing of riverbeds and the repair of hydraulic structures are carried out. The total completion rate is 61%. This week, work was completed at the facility in the Kamsko-Ustinsky district.
In addition, within the framework of 4 republican repair programs, the program for social service organizations has been completed by 78%. Over the past 2 weeks, one facility has been completed in Naberezhnye Chelny, Tyulyachinsky and Zelenodolsk districts. 70% of the work volume provided for in the program has been closed for forestry buildings. Contractors closed 41% of the planned volume for sports facilities. Work is underway in 13 institutions. 97% was achieved by the implementation of the program for the repair of buildings of the Ministry of Agriculture and Food. This week, 1 object was commissioned in the city of Bavly.
95% have been completed on the repair of executive committee buildings, 64% of military commissariats, 31% of municipal archives, 48% of magistrates' buildings, 40% of buildings subordinated to Rosgvardiya.