Modernization of the engineering infrastructure of the republic continues

5 August 2024, Monday

In terms of republican programs, the implementation of the drinking water supply program reached 56%. Work is currently underway at 43 sites in 30 districts. Over the past two weeks, work has been completed on 6 facilities in 6 municipalities of the republic.

The program of construction, reconstruction of networks and structures of wastewater disposal systems has been completed by 35% of the total volume. The progress of work on the program for the repair of gas consumption networks with the replacement of boilers in budgetary institutions is estimated at 88%. Over the past two weeks, work has been completed on 18 facilities in 17 districts.

56% of the total volume of construction and installation works was closed under the program for the reconstruction of gas distribution networks and indoor gas consumption networks with the installation of boilers.

According to the federal program for the modernization of municipal infrastructure, construction and installation works account for 68%. Currently, contractors are working on 36 sites.  12 objects have been completed.

 

SUBSCRIBE FOR NEWS
All content on this site is licensed under
Creative Commons Attribution 4.0 International