Today, the Ministry of Construction of Tatarstan held a regular meeting of the Republican Headquarters on preparation for the heating period. It was conducted by Alexey Frolov, First Deputy Minister of Construction, Architecture and Housing of the Republic of Tatarstan.
The work of the headquarters began with operational data monitoring information. In total, 3,012 boiler houses have been prepared in the Republic of Tatarstan, which is 94%. 3,220 or 99% of educational facilities are ready to start heating. 1,873 cultural facilities are ready – 98%, social protection facilities are ready by 96%, 98% of sports facilities are also ready to start heating.
The head of the Housing Inspectorate of the Republic of Tatarstan, Alexander Tygin, provided detailed information on the progress of major repairs of apartment buildings in the republic.
On the issue of preparedness for emergency response at enterprises of fuel and energy and housing and communal complexes in the future heating period, Alexey Frolov called on the staff members to take into account all the nuances discussed and use them in the upcoming heating period.
"Issues related to civil defense are reaching a high level. I ask the leaders to keep under control the issue of the safe life of citizens, including the uninterrupted functioning of heat supply," the Deputy minister said.