Capital repair programs for schools and educational centers have been fully implemented in Tatarstan

9 September 2024, Monday

Major renovation programs for schools and educational centers have been fully implemented in the Republic of Tatarstan. In the past two weeks alone, 23 facilities in 13 municipalities have been completed. In addition, 52 food units (out of 94) have been commissioned in 20 municipalities over the past two weeks, contractors have completed the last two resource centers (out of 4) in the Apastovsky and Drozhzhanovsky districts. The program for the repair of 15 dormitories has been completed with the commissioning of 4 facilities - two in Nizhnekamsk district and one each in Almetyevsk and Bugulminsky districts.

Such data was presented at a meeting in the Government House of the Republic of Tatarstan by the Minister of Construction, Architecture and Housing of the Republic of Tatarstan Marat Aizatullin.

Rustam Minnikhanov held a videoconference meeting with all municipal districts of the Rais of Tatarstan.

The Head of the Ministry of Construction of the Republic of Tatarstan reported on how the programs of major repairs of socio-cultural facilities, hydraulic structures and apartment buildings are progressing in Tatarstan.

The overhaul of preschool educational institutions has been completed by 98%. There is still 1 kindergarten in operation in the Mendeleevsky municipal district. This week, work has been completed on 6 sites in Leninogorsk, Aznakaevsky, Laishevsky, Verkhneuslonsky, Drozhzhanovsky and Nizhnekamsk districts.

Of the 138 facilities in the healthcare industry, two thirds are occupied by paramedic and obstetric centers. The completion of construction and installation work on them has reached 99%. 2 objects remain in operation. This week, one facility was completed in Rybno-Slobodsky and Alekseevsky districts.

The volume of work on the repair of 25 polyclinics is 96%. Work continues on 7 sites. Over the past two weeks, 3 facilities have been completed: one in Almetyevsk and two in Aktanyshsky districts.

 

The completion of major repairs of 31 medical hospitals is estimated at 81%. Contractors have commissioned one facility in Kazan and the Alekseevsky district over the past half a month.

The renovation of 24 cultural facilities is progressing. Of the 5 children's art schools, only the facility in Mamadysh remains in operation. The performance is 90%. Over the past two weeks, work has been completed on 3 sites in Leninogorsk, Menzelinsky and Sarmanovsky districts.

Construction and installation works on 19 cultural objects were completed by 84%. This week, work was completed at the facility in the Verkhneuslonsky district.

In the field of youth policy, 28 facilities are being renovated. Thus, repairs were carried out by 43% for 7 youth centers, 52% for 9 children's health camps, and 77% of the repair work for 6 youth clubs. Over the past two weeks, work has been completed at the facility in Zelenodolsk district.

The repair of psychological and pedagogical assistance centers has been completed by 42%.

21 objects are being implemented in the field of Ecology. The total completion rate reached 91%. 8 objects remain in operation.