The program for the repair of preschool educational institutions has been fully completed in the republic

2 November 2024, Saturday

This week, the republican program for the repair of preschool educational organizations has been fully completed with the completion of the last kindergarten in the Mendeleevsky district. This was announced at the republican meeting in the Government House of the Republic of Tatarstan by the First Deputy Minister of the Ministry of Construction of the Republic of Tatarstan Damir Shaidullin.

All 185 facilities for more than 5 billion rubles included in the field of education, consisting of 3 federal and 4 republican programs, have been closed. These are 21 kindergartens, 51 schools and educational centers, 94 food halls, 4 resource centers and 15 dormitories of secondary specialized educational institutions.

In the Healthcare sector, out of 138 facilities included in three federal and republican programs, work continues on 17. This is a polyclinic in the village.Kamskie Polyany (implemented within the framework of the national project "Healthcare"), where the work has almost been completed. Over the past 2 weeks, a polyclinic in Nizhnekamsk has been handed over.

16 facilities are in operation with contractors under the hospital repair program, the performance of which is estimated at 92%. Over the past two weeks, one facility has been completed in the cities of Kazan and Naberezhnye Chelny.

In the Youth Policy industry, out of 28 facilities, work continues on 4 youth centers – the total implementation of the program is 64%. Over the past two weeks, work has been completed at the facility in the Tukayevsky district.

For 6 children's health camps, the volume of work is closed by 82%. One facility in Kazan remains in operation under the renovation program for teen clubs. Its implementation is 45%.

Out of 5 children's art schools, only the facility in Mamadysh remains in operation for the repair of 24 objects of the Culture industry. Its implementation is 98%. Of the 19 cultural facilities, construction and installation work is underway on 6. Their total volume has reached 97%. Over the past two weeks, the facility in the Leninogorsk district has been completed.

 

 