Minister of Construction, Architecture and Housing and Communal Services of the Republic of Tatarstan Marat Aizatullin reported on the programs for the construction of social facilities and engineering infrastructure at a meeting at the Government House of the Republic of Tatarstan. Rustam Minnikhanov held a videoconference meeting with all municipal districts of the Rais of Tatarstan.
Of the educational institutions, construction and installation works on the building for primary classes in the Kukmor district are currently continuing, where 80% of the work is completed and 94% of the total volume is closed for 3 kindergartens.
In the Healthcare sector, out of 53 facilities under construction under 4 federal and republican programs, work continues on 3 medical institutions, where 97% of the implementation is available.
In the sports industry, out of 21 facilities, two football arenas (99% completed) and the administrative building of the existing football field in the village remain in operation. Apastovo, the implementation of which is 98%.
As part of the youth policy, 3 children's health camps out of 7 facilities are being renovated. The total implementation of the program is 83%. This week, the construction of one camp in the Alkeevsky district was completed. 88% of the work on the youth center in the village has been completed. Rybnaya Sloboda, which is under construction under the federal program "Modern appearance of rural areas".
According to the national Ecology project, work continues on the reclamation of silt fields from three sites (87% of the completion). Last week, a large-scale four-year work on the reconstruction of biological treatment facilities in Kazan was completed within the framework of the national Ecology project.
Of the 64 public spaces, the last object of the program, a park in the city of Naberezhnye Chelny, is at the final stage. This week, contractors commissioned one facility in the Yelabuga district.
The implementation of republican and federal programs for the modernization of engineering infrastructure is at the finish line. Of the 639 facilities, one facility in Kazan remains to be completed under the republican program for providing drinking water to the population. Its implementation is 40%. Over the past two weeks, work has been completed on 3 sites in Bugulminsky, Agryzsky and Verkhneuslonsky districts. Also, one facility in Kazan remains in operation under the federal program for the modernization of municipal infrastructure. Here, the volumes are closed by 91%.