Marat Aizatullin, Minister of Construction, Architecture and Housing and Communal Services of the Republic of Tatarstan, told today at a traditional meeting in the Government House of Tatarstan how programs for the construction of social facilities in various industries are being implemented in Tatarstan.
In healthcare, 4 out of 53 state contracts remain to be concluded. For example, auctions are scheduled for March 20 for the construction of 2 polyclinics and an admissions and diagnostic department in Kazan as part of the national project "Long and Active Life" and the republican program, and state contracts are scheduled for March 31. Construction and installation work has been completed by 20% in 47 medical and obstetric centers.
The construction of a general practitioner's center in the village of Vishnevka in Kazan continues. Construction and installation works on it account for 7%.
Out of 11 youth policy facilities, seven contracts remain to be concluded. Of the 3 youth centers, one auction is scheduled for March 11, the contract is scheduled for March 24, two auctions will be held on March 20, and government contracts are scheduled for March 31. At the same time, the contract for the construction of 4 children's health camps will be completed. State contracts have been concluded for 4 more camps. Work is already underway on three of them, including the facility in Sarmanovsky district, which has been operating since last year.
As for sports facilities, government contracts have been concluded for all 23. Contractors have started the construction of indoor football arenas in the Kukmorsky, Bavlinsky, Mendeleevsky and Arsky districts. Work continues on a transitional facility, the Football Development Center in Kazan.
In the Culture sector, of the 4 facilities planned for construction under the state program "Integrated Rural Development", only one remains to be signed – for the reconstruction of the regional house of culture in Mamadysh: the auction for it is scheduled for March 11, the state contract for March 24.
Contracts have been concluded for three multifunctional centers. Work is underway on one transitional MFC in Mamadysh – the total amount of work, taking into account the limits of last year, is 81%.
The construction of a boarding school for the elderly and disabled in Zelenodolsk district continues as part of the national Family project. The total completion rate for the facility is 41%.
In the field of Ecology, the implementation of a transitional facility included in the national project "Environmental Well-being" is continuing - the reclamation of the silt fields of Kazan. 88% of the work has been completed.