Today, at the republican meeting in the Government House of the Republic of Tatarstan, Minister of Construction, Architecture and Housing of the Republic of Tatarstan Marat Aizatullin spoke about the implementation of republican and federal programs for the construction of social facilities, public spaces and engineering infrastructure.
The meeting was held by the Rais of the Republic of Tatarstan Rustam Minnikhanov.
As the minister noted in his speech, to date, the readiness of 11 schools and outbuildings is 75%, the volume of construction and installation work for 10 kindergartens is 54% closed. In terms of the construction of facilities in the Healthcare industry, the completion of work on the construction of paramedic and obstetric stations is 65%, for other medical institutions, construction and installation work has reached 49%.
As for the construction of sports facilities, the performance of work on 4 football arenas is 24%, on universal playgrounds - 25%. Within the framework of the state program "Integrated rural development", the construction of a ski and roller track in Kukmor and the administrative building of the existing football field in the village continues. Apastovo. 28% of the work has been completed.
In the field of youth policy, within the framework of the republican program, the volume of work on the construction of children's camps has been completed by 33%, and the volume on the construction of a youth center in the village has been closed by 28%. Rybnaya Sloboda.
For the objects of the "Culture" industry, the implementation was 42%.
For the objects of the Ecology industry, work on the reconstruction of Biological treatment facilities has been completed by 83%, and the reclamation of silt fields - 67%. The reclamation of lands disturbed by oil-containing pollution in the village of Shemordan in Sabinsky district is 82%.
In addition, as part of the implementation of republican programs, the readiness of 7 executive committees today stands at 59%. The work on the points of comprehensive public services has been completed by 79%. This week, work was completed at the facility in the Yelabuga district.